Scheduling puzzles give you tasks, durations and dependencies and ask about minimum time, delays or which task is critical. They look intimidating but follow a simple routine: a forward pass to find the earliest finish of every task, then a backward pass to find the latest finish that does not delay the project. The difference between the two is the slack.
Key ideas
- Forward pass: earliest finish = latest earliest finish among prerequisites + duration.
- The project time is the largest earliest finish.
- Backward pass: latest finish of a task = earliest latest start among the tasks that depend on it.
- Slack = latest finish - earliest finish. Tasks with zero slack form the critical path.
- A delay on a critical task delays the whole project by the same amount.
Common traps
- Adding all durations instead of following dependencies.
- Forgetting that a task can start only when all prerequisites are complete.
- Assuming only one critical path when two can tie.
Practice set: A small project
A project has five tasks. A task can start only when all of its prerequisite tasks are complete, and there are enough workers to do any tasks in parallel.
| Task | Duration (hours) | Must be completed first |
|---|---|---|
| A | 3 | None |
| B | 2 | None |
| C | 4 | A |
| D | 2 | B |
| E | 3 | C and D |
Practice questions with solutions
Try each question first, then open the solution.
-
What is the minimum time needed to complete the project?
- A 10 hours
- B 7 hours
- C 9 hours
- D 14 hours
Show answer and solution
Answer: A. 10 hours
Earliest finish: A 3, B 2, C 7, D 4, E 10. The project ends at hour 10.
-
Which tasks lie on the critical path?
- A A, C and E
- B B, D and E
- C A, D and E
- D A, C and D
Show answer and solution
Answer: A. A, C and E
A + C + E = 3 + 4 + 3 = 10 hours, equal to the project time. B + D + E is only 7 hours.
-
How many hours of slack does task D have?
Type in the answer (no options).
Show answer and solution
Answer: 3
D finishes at hour 4 at the earliest. E starts at hour 7, so D can finish as late as hour 7. Slack = 7 - 4 = 3 hours.
-
If task C takes 6 hours instead of 4, what is the minimum time, in hours, to complete the project?
Type in the answer (no options).
Show answer and solution
Answer: 12
The chain A, C, E now takes 3 + 6 + 3 = 12 hours.
Keep practising
- Timed CAT DILR practice tests with full solutions
- Free full length CAT mocks to test pacing across all three sections
- CAT formula sheet and flashcards for quick revision
- CAT data interpretation: table practice
- CAT logical reasoning: arrangements practice